Butterfly Park at GHSS VAYAKKARA
60 different flowering plants were planted in 2 cents of land.
Programme Expenditure
Sl | Particulars | Amount |
---|---|---|
1 | Ground Clearance | 1800 |
2 | Plant purchasing | 4000 |
3 | Fertilizer | 1000 |
4 | Board | 200 |
5 | Refreshment | 1000 |
Total | 8000 |